I checked the signals of the IM OSEMs during the pump down. Just after starting the pressurization from 2.0Pa, the signals in count rapidly increased in 1 min.
I checked the signals of the IM OSEMs during the pump down. Just after starting the pressurization from 2.0Pa, the signals in count rapidly increased in 1 min.
[Tanaka, Hirose, Saito]
We matched the polarization of the sub-laser beam to that of the beam coming from the interferometer. Next, we increased the power of the beam coming from the interferometer by opening the iris. Then, we adjusted the alignment so that the sub-laser beam overlapped with the beam coming from the interferometer at the mirror just before the RFPD. As a result, we were able to observe the beat signal between the beam coming from the interferometer and the sub-laser beam.
[Kimura and Yasui]
Attached is the residual gas distribution during the SRM build-up test using the Qmass installed in the OMMT.
Since the pressure inside the Qmass analysis tube exceeded 1×10² Pa, the Qmass measurement was interrupted at 12:45 p.m. due to the interlock mechanism.
[Kimura, Yasui]
1. Build-up test
We had the build-up test by closing the GV between the duct and the pumping unit.
The slope of the pressure rise rate was approximately 0.6, which is the same rate as yesterday.
During the build-up test, I checked the rate of the pressure decrease with the TMP alone.
According to our logbook, when we tried to swich the vacuum pump from TMP to IP on 7 January 2026, we closed the GV between duct and pumping unit. At that time, the pressure value immediately droped from 2E-5 to 6E-6 Pa. Sine it took 1hour 47minites to reach the pressureof 6E-6Pa from 2E-5Pa this time, there seems to be something affecting the TMP performance.
2. Pressurization
We pressurized SRM again.
13:27 duct-side GV open
13:33 start pressurization 2.0Pa (cylinder pressure: 11.8 MPa)
13:40 3.0E3 Pa
13:57 1.0E4Pa
14:05 1.4E4pa
14:23 2.3E4Pa
14:37 3.0E4Pa
15:00 4.1E4Pa
15:08 4.7E4Pa
15:20 5.5E4Pa
15:30 5.9E4Pa(cylinder pressure: 1MPa->replace with a new cylinder(15.8MPa)
15:40 6.1E4Pa
16:00 7.3E4Pa
16:10 7.9E4Pa
16:20 8.7E4Pa(cylinder pressure:10.5MPa)
We will continue to pressurize it to atmospheric pressure on 30 April morning.
[Tanaka, Hirose, Saito]
We performed alignment to inject both the beam coming from the interferometer and the sub-laser beam into the RFPD. While the DC components of each beam were confirmed, the AC component of the interference signal could not be observed.
[kimura, hSawada, Yasui]
We had the build-up test again. The slope of the pressure rise rate was approximately 0.5 for the first 30minutes and then rose to about1.2.
During the buildup test, we checked the Q-mass data and found that the N₂/O₂ ratio was not 4, indicating that it differs from the composition of the air.
We also had the helium leak test, and a small leak ( ~1.0E-10 Pam^3/s) was detected on the +X-side-flange.
Finally, we replaced the dry pump with a repaired one to improve its performance.
The log-log plot of the SRM pressure after TMP startup indicates that the pressure is still decreasing.
[Ikeda, Sawada, Kimura, Takahashi]
We checked the leak of the geophone pods. First, the background level of the test chamber, which was taken from the CLIO site, was measured by the He leak detector. The level was smaller than the detectable limit, 1.0e-13 Pa ‣m^3 /s. After that, we measured the leak level of the H1, H2, and H3 geophoen pods one by one. In any case, the leak level was smaller than the limit.
I compared the vacuum evacuation speed this time with that at 28 February 2025.
Figure 1 shows the time trend of the vacuum pressure in 2025.
It takes 1 day and 7.5 hours to reach the pressure of 1.0e-4 Pa from 1.0e-2 Pa.
Figure 2 shows the time trend of the vacuum pressure this time.
After 1 day and 7.5 hours passed from the time that the vacuum pressure was 1.0e-2 Pa, the vacuum pressure was 1.9e-4 Pa.
Even after 2 day and 15 hours, the vacuum pressure was 1.2e-4 Pa.
So, the vacuum codition seems still worse thatn before.
I checked the signals of the IM OSEMs during the evacuation. The signals in count were increasing slightly during the pump-down with the DRY pump, due to the buoyancy. Just after switching the pump from the DRY to the TMP, the signals decreased rapidly in 10 min. The pressure change was from 10 Pa to 0.02 Pa. In this pressure region, the thermal conductivity of the gas changes a lot. I think this signal drop is due to the temperature change of the LED in the OSEMs.
I checked the IM transfer functions in a vacuum, changing the OSEM positions. The position in um was changed by the DC actuation of +10000 count to some COILOUTFs, as shown in the table. In any case, the behavior was almost the same (the DC gain of transfer functions is smaller than the reference, except for L).
| SAFE | TWR_FLOAT (without actuation) | Act. V2,V3 Plot1 | Act. V1 Plot2 | Act. H2,H3 Plot3 | |
| V1 | -139 | -335 | -246 | -183 | -313 |
| V2 | -139 | -250 | -150 | -209 | -235 |
| V3 | -190 | -304 | -205 | -264 | -291 |
| H1 | -351 | -351 | -363 | -341 | -355 |
| H2 | -283 | -278 | -275 | -265 | -207 |
| H3 | -201 | -207 | -197 | -196 | -143 |
I checked the IM transfer functions after the evacuation. The behavior reappeared in a vacuum. The DC gain of transfer functions is smaller than the reference, except for L.
[Hirose, Saito]
We constructed the optical layout for the PLL.
[mTakahashi, hSawada, Nakagaki, Yasui]
1. Vacuum evacuation by DSP
We tightened top- and +X-side- flanges of SRM, and started pumping down by the Dry Pump.
| 10:20 | Turned ON the dry pump |
| 10:26 | Opened the angle valve: 270 degrees |
| 10:38 | 6.8×10^4Pa |
| 11:06 | 2.9×10^4Pa |
| 11:14 | Opened the angle valve: 450 degrees |
| 11:30 | 9.2×10^3 ->Opened the angle valve fully |
| 11:36 | 6.6×10^3Pa |
| 11:47 | 3.7×10^3Pa |
| 13:25 | 6.6x10Pa |
| 13:37 | 5.3x10Pa |
| 13:56 | 4.0x10Pa |
| 14:09 | 3.3x10Pa |
2. Leak check of Q-mass
Also, we had a leak test around Q-mass that installed yesterday.
Since the leak level was less than 1×10^-13Pam^3/s, we opened the valve and connected to the OMMT chamber.
3. Vacuum evacuation by TMP
After rough pumping by the dry pump, I started evacuating by the TMP.
| SRM[Pa] | OMMT[Pa] | |
| 14:38 | 2.4x10 | 5.3x10^-1 |
| 14:39 | GVommt OPEN | |
| 1.3x10 | 1.4x10 | |
| 14:40 | TMP START | |
| 14:44 | 1.2x10 | 1.3x10 |
| 14:51 | 1.8x10^-2 | 2.2x10^-2 |
Date: 2026/04/24
Member: Dan Chen, Misato Onishi, Seiya Matsuo
We performed our usual WSK calibration at UToyama.
The results look no problem.
| Case | Alpha (Main Value) | Alpha (Uncertainty) |
| Front WSK, Back GSK | -0.911552 | 0.000128 |
| Front GSK, Back WSK | -0.910757 | 0.000131 |
Comparing with previous results, no significant issues were found.
Attached graph is the result summary including the latest measured data.
[Kimura, Tomaru, M. Takahashi, H. Sawada and R. Takahashi]
"Inspection results for the sealing surface of the +X side flange"
A vacuum leak in the range of 1×10⁻⁹ Pa·m³/s was detected, so we inspected the sealing surface of the side flange on the +X side.
As a result, we found a slight scratch on the elastomer surface.
Based on the location of the scratch, we believe it is the cause of the vacuum leak.
After installing a new elastomer on the sealing surface of the +X side flange, the flange was closed.
The flange fastening bolts are currently in a temporarily secured state.
"Inspection results for the sealing surface of the SRM top flange"
After removing the SRM top flange, the condition of the flange sealing surface was inspected.
No dirt or scratches were found on the surface of the elastomer.
Therefore, it was decided to reuse the SRM top flange as a seal.
Date of work:
23, Apr, 2026
Workers:
Kimura and Tomaru
Abstract:
We pressurized SRM atmospheric pressure for the investigation of outgassing source in SRM (k-log 36811).
The following is a record of the opening and closing of valves and the pressure of the pressurization process.
The same process is used for k-log 26030. It is noted here for reference.
~9:50 GVoomt Close
Set safety valve to SRM vacuum pump unit
Turn on main SW of TPM (Not acceration, only raise the rotor blades to protect the TMP)
9:55 Pressurization was started by G-2class grade air (klog-25912). Cylinder is filled with 7 m³ of compressed dry air.
Pressure inside SRM was 1.7 x 10^1 Pa Cylinder pressure 15.2 MPaG
10:00 " 2.1 x 10^3 Pa
10:22 " 3.7 x 10^3 Pa
10:33 " 4.2 x 10^3 Pa Cylinder pressure 14.2 MPaG
10:40 " 7.8 x 10^3 Pa
10:55 " 1.6 x 10^4 Pa Cylinder pressure 11.9 MPaG
11:21 " 3.3 x 10^4 Pa " 8.9 MPaG
11:30 " 3.9 x 10^4 Pa " 7.9 MPaG Increased air flow (Secondary pressure 1.1 kg/cm^2G)
11:34 " 4.1 x 10^4 Pa " 7.5 MPaG
11:54 " 5.3 x 10^4 Pa
12:12 " 6.4 x 10^4 Pa
12:12 " 6.4 x 10^4 Pa
12:19 " 6.9 x 10^4 Pa
12:27 " 7.4 x 10^4 Pa Cylinder pressure 2.0 MPaG
12:34 " 7.8 x 10^4 Pa " 1.1 MPaG
Change to a new cylinder filled with 7 m³ of compressed dry air
12:41 " 7.9 x 10^4 Pa Cylinder pressure 15.2 MPaG
12:45 " 8.1 x 10^4 Pa " 15.1 MPaG
12:53 " 8.4 x 10^4 Pa
12:58 " 8.9 x 10^4 Pa
13:02 " 9.0 x 10^4 Pa " 13.2 MPaG
13:04 " 9.1 x 10^4 Pa
13:07 " 9.4 x 10^4 Pa " 12.6 MPaG
13:10 " 9.6 x 10^4 Pa
13:11 " 9.7 x 10^4 Pa
The pressurization process is terminated because the pressure in the SRM has reached almost atmospheric pressure at 13:11.
Based on the volume of dry air, the internal volume of the SRM was estimated to be approximately 9 m³.
[mTakahashi, hSawada, Nakagaki, Yasui]
1. Vacuum evacuation by DSP
We tightened top- and +X-side- flanges of SRM, and started pumping down by the Dry Pump.
| 10:20 | Turned ON the dry pump |
| 10:26 | Opened the angle valve: 270 degrees |
| 10:38 | 6.8×10^4Pa |
| 11:06 | 2.9×10^4Pa |
| 11:14 | Opened the angle valve: 450 degrees |
| 11:30 | 9.2×10^3 ->Opened the angle valve fully |
| 11:36 | 6.6×10^3Pa |
| 11:47 | 3.7×10^3Pa |
| 13:25 | 6.6x10Pa |
| 13:37 | 5.3x10Pa |
| 13:56 | 4.0x10Pa |
| 14:09 | 3.3x10Pa |
2. Leak check of Q-mass
Also, we had a leak test around Q-mass that installed yesterday.
Since the leak level was less than 1×10^-13Pam^3/s, we opened the valve and connected to the OMMT chamber.
3. Vacuum evacuation by TMP
After rough pumping by the dry pump, I started evacuating by the TMP.
| SRM[Pa] | OMMT[Pa] | |
| 14:38 | 2.4x10 | 5.3x10^-1 |
| 14:39 | GVommt OPEN | |
| 1.3x10 | 1.4x10 | |
| 14:40 | TMP START | |
| 14:44 | 1.2x10 | 1.3x10 |
| 14:51 | 1.8x10^-2 | 2.2x10^-2 |
I compared the vacuum evacuation speed this time with that at 28 February 2025.
Figure 1 shows the time trend of the vacuum pressure in 2025.
It takes 1 day and 7.5 hours to reach the pressure of 1.0e-4 Pa from 1.0e-2 Pa.
Figure 2 shows the time trend of the vacuum pressure this time.
After 1 day and 7.5 hours passed from the time that the vacuum pressure was 1.0e-2 Pa, the vacuum pressure was 1.9e-4 Pa.
Even after 2 day and 15 hours, the vacuum pressure was 1.2e-4 Pa.
So, the vacuum codition seems still worse thatn before.
I checked the IM transfer functions after closing the chamber. The behavior did not change after opening the chamber to remove the geophone pods.