[Ushiba, Komori]
We observed frequent excitation of the IX TM oplev pitch signal at 1 Hz.
This appears to be caused by glitches injected into the GAS filters, which excite the 1-Hz length mode of the cryo-payload, as shown in the figure.
According to Ushiba-san, the glitches in the GAS filters occur when the GAS is at a specific operating point.
[Tanaka, Ushiba, Komori]
We continued the investigation of the GR–IR coupling issue.
We successfully identified a configuration without the coupling, in which the DC power for the whitening board is supplied by an independent power supply.
A possible cause of the issue might be instantaneous saturation of the power supply during IFO flashing.
This work is a continuation of yesterday’s investigation (klog:36533).
First, we inserted an RF transformer (T1CA) between PDA3 and the demodulator after measuring the transfer function of the transformer (gain ≈ −1 dB, phase delay ≈ 1 deg).
However, the noisy behavior did not change after inserting the transformer.
The related measurement results are shown in Fig.1.
Next, we checked whether the noisy spectrum depends on which board the cable is connected to.
The spectrum did not become noisy when the cable was connected to the demodulator, but it became noisy when the cable was connected to the whitening board.
Therefore, we tried using an independent whitening board outside the rack with an independent power supply.
With this configuration, we confirmed that the spectrum remained quiet.
In contrast, the spectrum became noisy when we used the power supply inside the rack to drive even the independent whitening board (Fig.2).
Finally, we measured the spectrum using the original whitening board inside the rack but powered by the independent power supply.
The spectrum remained quiet even without the RF transformer (Fig.3).
This result indicates that the coupling issue can likely be resolved by using an independent power supply for the whitening board.
We suspect that a possible cause of this issue is instantaneous saturation of the power supply during IFO flashing.
We found that the whitening board draws a relatively large current, approximately 0.7 A at +18 V and 0.4 A at −18 V.
In addition, we checked the rack power supply located in the computer room, which currently outputs approximately 17 A, while the protection threshold is set to 21 A.
Therefore, such saturation could plausibly occur.
Tomorrow, we will measure the spectrum with the PDA1 and PDA2 cables connected to their corresponding whitening boards, which will be powered by the independent power supply.
[Takahashi.R, Washimi, Hirata]
We have completed the installation of the IRM damper’s mechanical parts and in-vac cabling. Suspention is still locked, so we have not operated IRM damper yet.
1. Exchange dummy plates to magnet plates
IRM has 3 dummy plates. We removed them(pic1). After that, we assembled the plates with the IRM, which already had the magnets glued on by Takahashi-san. (klog 36517)(pic2)
2. Install coil base
Only coil base part are installed first.(pic3)
3. Install coils
3 coils are connected to 1 cable. Pins and sockets are covered by PEEK shrink(pic4). 3 coils are installed at the same time. (pic5)
The cables got tangled, and it took a while to untangle them. The relay connector was mounted on a nearby pole, and cable from the coil was connected to it.(pic6)
We checked resistance at the relay connector.
・Coil #1: 6.3 ohm
・Coil #2: 6.5 ohm
・Coil #3: 6.3 ohm
4. Coil alignment
Coil base can move 3 degrees of freedom, and coil 's angle can be adjusted using 6 screws. 3 Coils are aligned with magnet using those mechanics.
5. Exchange Feed through panel
We replaced the feedthrough panel, which previously had only thermometer connected, with 4 connector feedthrough. (pic7)
6. Continuity check
After connecting all in-vac cables, we did continuity check at the outside of feedthrough.(pic8)
・Coil#1: 7.6 ohm
・Coil#2: 7.9 ohm
・Coil#3: 7.7 ohm
We checked thermometer cables too.
・Thermometer1-6: 111.1 ohm
・Thermometer2-7: 111.5 ohm
Today's photo is here: https://www.dropbox.com/scl/fo/0lwieoxtf72h3d59xim6g/AMqNUPbwqT_vkmvjlaAGhMk?rlkey=scefj78rth7kpcsnq352ibedp&st=6qtyal01&dl=0
[Alex, Yokozawa]
We entered the PSL room to conduct a tapping test on several mirrors to help identify peaks due to beam jitter in DARM. We confirmed that the peak around 215 Hz comes from M17 and that the group of peaks around 450 Hz comes from the periscope. We also identified the peaks around 350 Hz as coming from M18 and the peak around 150 Hz as coming from M16. We had issues connecting to the ipad which made peak identification more difficult so we plan to try again tomorrow.
We then did a tapping test on the IMC REFL Table and found that the 150 Hz comes from the beamsplitter that splits the light off for the WFSs from the main path.
M17 - 215 Hz
Periscope - 450 Hz (2 peaks) or four peaks (one either side of the main two) when tapped at bottom. Also saw some of the 350 Hz peaks when large excitation
M16 - 150 Hz , 250 Hz
M18 - 350 Hz two peaks
REFL Table
150 Hz peak is from beamsplitter that splits off the QPD path from the PD path
[Kimura, Yasui, M. Takahashi, H. Sawada, R. Takahashi, Hirata and Washimi]
On March 9, from 8:30 to 9:00, the pressure inside the SRM was increased from 87 kPa (k-log 36520) to atmospheric pressure (~98 kPa).
After pressurization, the top flange and two side flanges of the SRM were opened.
I offloaded the following GAS filters with the FRs.
[Tanaka, Ushiba, Komori]
We started investigating a mysterious coupling between the IR flashing and the green PDH signals.
Our initial tests suggest that the coupling is likely mediated through the RF signals of the IR RFPDs.
The issue of the mysterious IR–GR coupling has persisted for a long time.
Due to this issue, we cannot open the shutter in front of the REFL QPDs or increase the power at the out-of-loop CARM PD, and we frequently suffer from lock losses during the IR handover stage.
If this issue can be resolved, a significant improvement in several operational aspects is expected.
To investigate the origin of this issue, we compared the power spectrum of the ALS DARM signal under several configurations, as shown in the figure.
The reference spectra are the blue and green lines, where the PRM is misaligned and aligned after the IR finds resonance with the conventional cable connections, respectively.
IR flashing clearly produced a noisy DARM spectrum, consistent with the noisy behavior observed in the time-series data.
First, we turned off all REFL PDs by switching off the PD power supply board, and we did not observe the additional noise (brown).
Next, we focused on one of the problematic PDs, REFL PDA3, with the PD power supplies for PDA1 and PDA2 turned off and only PDA3 powered on, while the RF output signal was terminated (magenta).
We did not observe additional noise in either case.
This result suggests that the issue is not caused by a simple cable connection without the power supply, but rather by the connection between an operating PD and the demodulator.
Next, we measured the noise with PDA3 connected using a different cable instead of the conventional one.
In this case, the noise reappeared (green), indicating that the issue does not depend on the cable routing.
Tomorrow, we will test the effect of inserting an RF transformer (T1CA made by R&K), which isolates the ground and blocks the DC signal between the input and the output.
[Takahashi, Washimi, Hirata]
We did preparation for installation of SRM IRM dampers.Today, we locked suspension, and Breadboard. After that we removed Mid-size baffles from the breadboard.
1. Lock IP and Topfilter
After opening the top flange of chamber, we locked IP and Topfilter. We covered suspension by Seiden-sheet. (Guardian status was already SAFE mode.)
2. Check the mirror height
We checked the mirror height by laser leveler. Beam height is indicated on SRM chamber(Main mark is on +Y+X side. Copy is on -Y+X side. pic1, pic2 )
Unfortunately, Beam height is close to the edge of side flange. So laser leveler could only be used near the center.(pic3) We put green laser leveler at the +X side, and align to the Beam height mark on the chamber.
And put red laser leveler at -X side, and align it to the +X side green laser leveler(pic4). Recoilmass front ring has center mark. We can see the laser leveler height and the recoilmass center line.
・+X side (Green line) looks same as recoilmass center line.(pic5)
・-X side (Red line) looks 3 millimeters away from the recoilmass.(pic6)
3. Check the Bread board height
Laser leveler can only used around center of side flanges. So we can only check the height near the center.
・+X side (Green line) is 380.5mm.(pic7)
・-X side (Red line) is 383.0mm.(pic8)
4. Lock the Breadboard
Turn 4 foot screws to lower that until they touch the block. After that, added 4 masses(Total 20kg) on the breadboard for locking. (pic9)
5. Lock the Suspention
Bottomfilter, IMR, IM, RM and TM were locked.
6. Mark the Mid-size baffle position
To record the current baffle positions, 3 blocks(AL clamps) were set on each baffle.(pic10)
7. Remove Mid-size baffles
We removed 4 fixed clamps, and removed mid-size baffles(AR side and HR side). Clamps for the mid-size baflles remain on the bread board.(Note that those positions have been changed.) (pic11)
Removed Mid-size baffles are on the tables have 4 pillars, and wrapped by plastic films. 4 pillars preventing plastic film touch baffles. (pic12)
*We weighed removed baffles.
・HR side : 4.94kg
・AR side : 4.931kg
Today's pictures are https://www.dropbox.com/scl/fo/1dw0adstbz35z85i0vd91/AJlOguQbuxD332fX1ZaIiYE?rlkey=xv1ztcd0wli70ukd0hxlslcl0&st=sfhiadap&dl=0
[Takahashi.R, Washimi, Hirata]
We have completed the installation of the IRM damper’s mechanical parts and in-vac cabling. Suspention is still locked, so we have not operated IRM damper yet.
1. Exchange dummy plates to magnet plates
IRM has 3 dummy plates. We removed them(pic1). After that, we assembled the plates with the IRM, which already had the magnets glued on by Takahashi-san. (klog 36517)(pic2)
2. Install coil base
Only coil base part are installed first.(pic3)
3. Install coils
3 coils are connected to 1 cable. Pins and sockets are covered by PEEK shrink(pic4). 3 coils are installed at the same time. (pic5)
The cables got tangled, and it took a while to untangle them. The relay connector was mounted on a nearby pole, and cable from the coil was connected to it.(pic6)
We checked resistance at the relay connector.
・Coil #1: 6.3 ohm
・Coil #2: 6.5 ohm
・Coil #3: 6.3 ohm
4. Coil alignment
Coil base can move 3 degrees of freedom, and coil 's angle can be adjusted using 6 screws. 3 Coils are aligned with magnet using those mechanics.
5. Exchange Feed through panel
We replaced the feedthrough panel, which previously had only thermometer connected, with 4 connector feedthrough. (pic7)
6. Continuity check
After connecting all in-vac cables, we did continuity check at the outside of feedthrough.(pic8)
・Coil#1: 7.6 ohm
・Coil#2: 7.9 ohm
・Coil#3: 7.7 ohm
We checked thermometer cables too.
・Thermometer1-6: 111.1 ohm
・Thermometer2-7: 111.5 ohm
Today's photo is here: https://www.dropbox.com/scl/fo/0lwieoxtf72h3d59xim6g/AMqNUPbwqT_vkmvjlaAGhMk?rlkey=scefj78rth7kpcsnq352ibedp&st=6qtyal01&dl=0
Ushiba, Komori, Tanaka
We tempolary replaced the LO to the other one, which was used PLL before (fig.1). Now, GRX could be locked.
Ushiba, Yokozawa, Tanaka
This morning, we found that GRX could not be locked even though the flash amount seemed to be large enough (> 0.8 from the view of K1:LSC-TR_GRX_NORM_OUT_DQ ). According to the GRX PDH error signal channel (K1:ALS-X_PDH_MIXER_DAQ_OUT), Any PDH-like signals seem to be not observed. However, since the DC power on the PD has some responce whenever GRX was flashed, the PD for PDH itself seems to be turned on. Also, CMS seems to be turned on because K1:ALS-X_PDH_MIXER_DAQ_OUT has some responses when we operated some switches on the CMS. So we suspected that the LO has something wrong.
Yokozawa-san and I entered mine and confirmed the LO and the CMS for PDH were turned on. Then, we checked whether the LO emitted the 33 MHz signal or not by using Moku:lab. However, we could not obsered any signal at 33 MHz. (This time, we confimed Moku:lab could be observed the output of GRY LO which emited the signal with the almost same amplitude at different frequencies.)
We tried to solve it by restarting the LO but the situation was not changed. After this, we found that the "UNLOCK" and "ERR" sign were shown on the display. we checked the error messages. There are many error messages (fig.1).
According to the manual, we need to ask the manufacturer to fix the LO in the case that their messages are shown. This afternoon, we will bring the other RF generator from Mozumi and try to solve this issue by replacing the LO.
Ushiba, Komori, Tanaka
We tempolary replaced the LO to the other one, which was used PLL before (fig.1). Now, GRX could be locked.
I commented out all the request for SRM in te LSC_LOCK guardian and INITIAL_ALIGNMENT guardian.
These guardians can be used without conflicting SRM hardware work now, so I executed these guardians.
The Check 3 script has been developed and tested.
The comparison between the LL spectrum and the RAW-based reconstructed spectrum shows generally good agreement.
Detailed Working Logs:
I offloaded the F0 and F1 GAS filters in IX with the FRs.
I offloaded the following GAS filters and IP with the FRs.
[Kimura and Yasui]
Temperature calibration data was registered to Y-end Cryocon.
The registration date and time were March 6, 2026, 11:00 AM to 11:30 AM.
The name of the Cryocon to which the temperature calibration data was registered is EY2: Duct Shield 1.
The registered temperature calibration data is the resistance/temperature curve for a platinum-cobalt resistance thermometer (PtCO).
After registering this temperature data, the temperature calibration data for channels D to H channels of EY2: Duct Shield 1 were changed from platinum resistance thermometer (Pt100) to PtCO.
The resulting temperature difference at room temperature was +2 K.
This temperature difference increases significantly at cryogenic temperatures.
[Kimura and Yasui]
From 13:30 to 16:30 on March 6, the SRM was pressurized to 87 kPa with compressed air below the dew point of -40 Celsius degrees.
It will continue to be pressurized to atmospheric pressure on March 9 morning.
Soon after Type-A suspensions are aligned, both GRX and GRY flashes inside the arm cavities.
So, no serious misalignment happens during the blackout.
Though saturation of the actuators occured, all VIS finaly reached the LOCK_ACQUISITION state after offloading actuators.
Since ITMX F0 GAS and ETMY IP H2 actuators are saturating, they should be offloaded again.