Reports of 34724
ISC (General)
shun.saito - 18:59 Monday 31 August 2026 (37436) Print this report
PRCL/SRCL Measurement with P-Polarization

[Fujimoto, Yokozawa, Saito]

A mirror was installed inside the OMMT chamber so that the light reflected from OMMT2 would reach the optical table on the X+ side. The reflected light was then directed into the RFPD. However, the DC output was approximately 1.3 V, with fluctuations in the signal also observed. Since the DC output was several volts when the RFPD was placed at OMC REFL, the position of the RFPD will be fine-tuned next time to maximize the DC output, and the condition of the RFPD will also be investigated.
 

  • First, a mirror was installed inside the OMMT chamber so that the light reflected from OMMT2 would reach the optical table on the X+ side (Photo 1). The beam was then lowered using a periscope, and the optical power was measured to be approximately 12 mW. An ND filter with OD = 1.0, a mirror, a lens with a focal length of 50 mm, and the RFPD were then installed. The optical power measured just before the RFPD was approximately 1.5 mW. Next, a rotatable polarizer was placed in front of the lens (Photo 2), and the polarizer angle was adjusted to maximize the optical power. The measured power was approximately 1.0 mW. The BNC cable that had been used for the OMC REFL PD was then connected to the DC output of the RFPD so that the signal could be monitored through CDS. The mirror alignment was adjusted to maximize the DC count, resulting in approximately 2200 counts, corresponding to approximately 1.3 V. When the RFPD was placed at OMC REFL and approximately 1 mW of light was injected, the DC output reached several volts after optimizing the mirror alignment. Therefore, it is likely that not all of the incident light is being coupled into the RFPD. Fluctuations in the signal were also observed. Next time, the position of the RFPD will be fine-tuned to maximize the DC output, and the condition of the RFPD will be investigated.
Images attached to this report
VIS (IX)
takafumi.ushiba - 18:43 Monday 31 August 2026 (37435) Print this report
Comment to ITMX NBDAMP_P2 was turned off (37424)

I checked the guardian and found that this filter was not implemented into the guardian, so this filter should be turned on manually at some point.
I also checked when the filter was turned on (fig1) and checked the klog around that  day but I could not find the related log.

If this filter is really necessary, it should be turned on again, and also be managed by the guardian.

Images attached to this comment
VIS (General)
takafumi.ushiba - 18:19 Monday 31 August 2026 (37434) Print this report
Comment to VIS trip recovery (37425)

I checked ETMX and ETMY suspensions by engaging local controls step by step.
There seems no serious issue and both suspensions can reach LOCK_ACQUISITION state without any problems.

CRY (Cryostat EX)
hiromi.yasui - 17:36 Monday 31 August 2026 (37433) Print this report
Comment to Started heating the X-end cryo-duct shields (37370)

[Nakagaki, Yasui]

I tried to turn off the heater on the 8K shield, but this power output was already 0W.

We checked the situation and found that the AC alarm was active on this power supply.

It appeart that the heater shut off due to a drop in the input valtage.

According to the temperature of the 8K shield top, the heater appeared to have stopped before 8:31(JST) on Aug 27.

Around this time we experienced a momentary power outage at this site.(klog 37420)

We checked the resistance of this heater and found no issues.

Anyway, we completed the pre-heating work.

Images attached to this comment
ISC (General)
takaaki.yokozawa - 11:33 Monday 31 August 2026 (37432) Print this report
Evaluation toward the beam position measurement at the surface of OMMT1 shield
(Many calculation and evaluation was done by Chat GPT, so there are possibility to have mistake)

From the past evaluation of the beam position at the GV, OMMT1, klog20830, we evaluated the radius and so on.
Very rough evaluation, the radius of GV would be 50 mm and shield in front of OMMT1 was 45 mm, so we can see the clipping of beam at the shield of OMMT1 before clipping on the GV, I think.

Images attached to this report
VAC (OMMT)
hiromi.yasui - 15:38 Friday 28 August 2026 (37431) Print this report
Comment to Opened vcauum chamber OMMT (37429)

[Kimura, Yasui]

We vented OMT-OMMT chamber to atmospheric pressure.

9:17 Turned off the interlock system for GVommt / 3.3*10^-5 Pa

9:24 Closed the GVommt / 9.1*10^-4 Pa

9:32 Started pressurization / opened the ball valve about 15 degrees and the angle valve by two turns)

9:35 3.5*10^2 Pa

9:55 3.1*10^3 Pa

9:59 Increased air flow (opened the ball valve fully and the angle valve by two turns)

10:19 1.0*10^4 Pa

10:35 1.6*10^4 Pa

10:42 Increased air flow ( increased the regulator's secondary pressure from 1.5 to 2.0 kgf/cm^2 and opened the angle valve by two turns)

10:55 2.8*10^4 Pa

11:30 5.7*10^4 Pa

12:00 8.1*10^4 Pa

12:14 9.4*10^4 Pa ->9.6*10^4 Pa

 

Images attached to this comment
VAC (OMMT)
takashi.uchiyama - 13:40 Friday 28 August 2026 (37429) Print this report
Opened vcauum chamber OMMT
2026/08/28
Yasui, Kimura, mTakahashi, Sawada

After the venting work, we opened flanges ( 2-6, 2-8) of the OMMT chamber.
Comments to this report:
hiromi.yasui - 15:38 Friday 28 August 2026 (37431) Print this report

[Kimura, Yasui]

We vented OMT-OMMT chamber to atmospheric pressure.

9:17 Turned off the interlock system for GVommt / 3.3*10^-5 Pa

9:24 Closed the GVommt / 9.1*10^-4 Pa

9:32 Started pressurization / opened the ball valve about 15 degrees and the angle valve by two turns)

9:35 3.5*10^2 Pa

9:55 3.1*10^3 Pa

9:59 Increased air flow (opened the ball valve fully and the angle valve by two turns)

10:19 1.0*10^4 Pa

10:35 1.6*10^4 Pa

10:42 Increased air flow ( increased the regulator's secondary pressure from 1.5 to 2.0 kgf/cm^2 and opened the angle valve by two turns)

10:55 2.8*10^4 Pa

11:30 5.7*10^4 Pa

12:00 8.1*10^4 Pa

12:14 9.4*10^4 Pa ->9.6*10^4 Pa

 

Images attached to this comment
CRY (Cryostat EX)
takashi.uchiyama - 13:38 Friday 28 August 2026 (37428) Print this report
Comment to Started heating the X-end cryo-duct shields (37370)
2026/08/28
uchiyama

Since the temperature of the EX duct shields reached over 280K as shown Fig. 1, we stopped the heaters of the duct shields at 13:30. Now only the heater on the radiation shield is working.

Fig. 2 shows current source for the heater of the Arm side cryocooler.
Fig. 3 shows current source for the heater of the BRT side cryocooler.
Images attached to this comment
DGS (General)
satoru.ikeda - 12:55 Friday 28 August 2026 (37427) Print this report
Comment to Momentary Power Outage and Computer Reboots at Both End (37420)

Included for informational purposes

A follow-up investigation found that, according to information from Hokuriku Electric Power Company, a power outage occurred in Kamioka at around the same time (08:22 on August 27, 2026), and power was automatically restored.
Although it isn't included in the town's name, so I can't say for sure, it may have been related.
 

Images attached to this comment
Non-image files attached to this comment
DGS (General)
satoru.ikeda - 12:23 Friday 28 August 2026 (37426) Print this report
Comment to Momentary Power Outage and Computer Reboots at Both End (37420)

Nakagaki-san, ikeda

The ETMX Picomotor controller had remained powered off.

The Picomotor controller had not been turned back on following the electrical equipment inspection with a blackout in March.

This issue was unrelated to the cause of the real-time PC reboot.

Corrective action:
We powered on the controller and confirmed that it could be accessed via MEDM.
 

Non-image files attached to this comment
VIS (General)
takashi.uchiyama - 9:25 Friday 28 August 2026 (37425) Print this report
VIS trip recovery
2026/08/28

Uchiyama

When I requested ITMX to misaligned state, ITMX was tripped.
SO I recovered the situation according to the document.

Images attached to this report
Comments to this report:
takafumi.ushiba - 18:19 Monday 31 August 2026 (37434) Print this report

I checked ETMX and ETMY suspensions by engaging local controls step by step.
There seems no serious issue and both suspensions can reach LOCK_ACQUISITION state without any problems.

VIS (IX)
takafumi.ushiba - 9:24 Friday 28 August 2026 (37424) Print this report
ITMX NBDAMP_P2 was turned off

Since ITMX NBDAMP_P2 didn't turn off automatically when ITMX went PAY_TRIPPED state, I manually turned off NBDAMP_P2.
If this filter is not managed by the guardian, the guardian should be changed.

Comments to this report:
takafumi.ushiba - 18:43 Monday 31 August 2026 (37435) Print this report

I checked the guardian and found that this filter was not implemented into the guardian, so this filter should be turned on manually at some point.
I also checked when the filter was turned on (fig1) and checked the klog around that  day but I could not find the related log.

If this filter is really necessary, it should be turned on again, and also be managed by the guardian.

Images attached to this comment
VIS (IY)
ryutaro.takahashi - 17:35 Thursday 27 August 2026 (37423) Print this report
Comment to Offload of GAS filters (36614)

I offloaded the BF GAS with the FR.

VIS (EX)
ryutaro.takahashi - 17:35 Thursday 27 August 2026 (37422) Print this report
Comment to Offload of GAS filters (36707)

I offloaded the F0, F1, F3, and BF GAS filters with the FRs.

FCL (Clean Area)
takashi.uchiyama - 11:36 Thursday 27 August 2026 (37421) Print this report
Cleanng of EXC
2026/08/27

Hayakawa, Sawada, mTakahashi, Omae, Yamaguchi, Uchiyama

We performed cleaning the EXC booth as follows.

EXC cleaning range (scheduled for 08/27/2026, 9/1-2)
- EXC booth 1F area (excluding the 2nd floor up by stairs)
- The stairs to the 2nd floor of the EXC booth are within the cleaning range (the back of the stairs directly above the refrigerator to be replaced is also cleaned)
- TMSX is out of range

EXC cleaning
- When cleaning, wear clean underwear, head cap, mask, clean gloves, and clean shoes
- Use a vacuum cleaner equipped with a HEPA filter to clean the floor of the first floor in the clean booth: 1 time
- Use an adhesive roller to remove dust from the first floor in the clean booth: 1 time
- Use a low-dust wiper moistened with pure water to wipe and clean the surface of the vacuum chamber and the vacuum duct: 1 time
- Use a low-dust wiper moistened with pure water to wipe and clean the anti-static sheet wall: 1 time
- Use an adhesive roller and a vacuum cleaner with a HEPA filter to clean the first floor in the clean booth again: 1 time (2nd time)
- Wipe and clean the floor surface on the first floor using a mop with a low-dust wiper moistened with pure water: 1 time
- Remove the aluminum foil from the work desk in the booth and wipe it.
- Especially dirty floors are cleaned with electrostatic sheets after cleaning.
DGS (General)
satoru.ikeda - 10:20 Thursday 27 August 2026 (37420) Print this report
Momentary Power Outage and Computer Reboots at Both End

At approximately 08:22:44 JST on August 27, 2026, a momentary power outage occurred at both end, causing four computers k1ex1, k1ex0, k1ey1, and k1ey0 to reboot. All four computers were back online by 08:25:19 JST.
The ADC and DAC cards were recognized normally, indicating that the I/O chassis likely continued operating without interruption.
Only k1ey0 showed an unusually high IRIGB_TIME value of 27, compared with the normal value of approximately 11. To restore it to normal, all real-time models on k1ey0 were restarted.

Regarding systems other than the real-time models, the Picomotor controller cannot be reached by ping from k1ex1. This issue may be unrelated to the power outage, but it appears to require an on-site inspection and will be checked during the next visit.
 

Images attached to this report
Non-image files attached to this report
Comments to this report:
satoru.ikeda - 12:23 Friday 28 August 2026 (37426) Print this report

Nakagaki-san, ikeda

The ETMX Picomotor controller had remained powered off.

The Picomotor controller had not been turned back on following the electrical equipment inspection with a blackout in March.

This issue was unrelated to the cause of the real-time PC reboot.

Corrective action:
We powered on the controller and confirmed that it could be accessed via MEDM.
 

Non-image files attached to this comment
satoru.ikeda - 12:55 Friday 28 August 2026 (37427) Print this report

Included for informational purposes

A follow-up investigation found that, according to information from Hokuriku Electric Power Company, a power outage occurred in Kamioka at around the same time (08:22 on August 27, 2026), and power was automatically restored.
Although it isn't included in the town's name, so I can't say for sure, it may have been related.
 

Images attached to this comment
Non-image files attached to this comment
VIS (General)
takashi.uchiyama - 9:16 Thursday 27 August 2026 (37419) Print this report
VIS trip recovery
2026/08/27

Uchiyama

Due to the sudden power outage, ETMX and ETMY were tripped. I reset the trip according to the document.

Images attached to this report
AEL (General)
Shigenori Moriwaki - 14:54 Wednesday 26 August 2026 (37417) Print this report
RFQPD and RFPD stocktaking
[Aoumi, MShigen, Shimode]

In the morning of 2026-08-25, we confirmed the locations of stock RFQPDs and RFPDs to consider the possibility of the use at NAOJ Mitaka.

RFQPDs:
S1706958 (Enclosure S_No.018) and
S1706959 (Enclosure S_No.019)
were found in the IMC duct-side desiccator.

RFPDs:
S1706774 (Enclosure S_No.003) and
S1706829 (Enclosure S_No.001)
were found in the PSL room desiccator.
Images attached to this report
FCL (Clean Area)
takashi.uchiyama - 13:27 Wednesday 26 August 2026 (37416) Print this report
Cleaning OMC-OMMT
2026/08/26

Hayakawa, Sawada, mTakahashi, Omae, Yamaguchi, Uchiyama

We set "ASC_LOCK guardian" and "VERTEX guardian" DOWN state before closing the laser shutter at 8:35.
We turned on the FFUs of the OMC-OMMT-SRM booth at 8:40.

We cleaned the clean booth floor from OMC to SR3 with lint rollers.
We moved the metal shelf and so on to make a path for installing the optical table.
We cleaned the optical table and then installed it near the OMMT chamber.
Images attached to this report
ISC (ASC)
hirose.chiaki - 16:40 Tuesday 25 August 2026 (37415) Print this report
Comment to IMMT2 ADS modification (37413)

I updated the Guardian for the DRMI ADS preparation so that the following parameters are automatically set:

  • IMMT2 excitation frequency, amplitude, and phase
  • Common filters for the BP and I signals
  • Notch filters
Images attached to this comment
ISC (General)
takafumi.ushiba - 16:30 Tuesday 25 August 2026 (37414) Print this report
Modiication of VERTEX guardian

I modified LOCKING_DRMI_1F state as follows (see also fig1).

1. Change gains of MICH1, PRCL1, and SRCL1 filter bank to 1 to avoid kick of the suspension during the lock acquisition (self.counter = 0).
2. Increasing gains of MICH1, PRCL1, and SRCL1 fiter bank to 9, 1.7, and 1.4, respectively after DRMI is locked (self.counter == 2).
3. Turning off MICH2, PRCL2, and SRCL2 gains when suspension waskicked during the lock acquisition to avoid additional kick before calm down (self.counter == -1).

Images attached to this report
ISC (ASC)
kenta.tanaka - 16:25 Tuesday 25 August 2026 (37413) Print this report
IMMT2 ADS modification

Ushiba, Hirose, Tanaka

We modified IMMT2 ADS so that we can implement resG filters in PRCL, SRCL, and MICH controls to suppress the peaks at IMMT2 dither frequencies in their error signals.

We changed the dither frequencies from 30.125 Hz and 32.125 Hz to 9.125 Hz and 19.125 Hz and performed the phasing for these frequencies (fig.1).

According to the phasing results, we set the demod. phases. Also, There seem to be some peaks at -0.875 Hz and +1.125 Hz in bandpassed signals. So we implemented the notch filters for 0.875 Hz and 1.125 Hz in DEMOD_SIG_I.

After that, we engaged IMMT2 ADSs. They seem to work well. 

Images attached to this report
Comments to this report:
hirose.chiaki - 16:40 Tuesday 25 August 2026 (37415) Print this report

I updated the Guardian for the DRMI ADS preparation so that the following parameters are automatically set:

  • IMMT2 excitation frequency, amplitude, and phase
  • Common filters for the BP and I signals
  • Notch filters
Images attached to this comment
ISC (General)
takafumi.ushiba - 16:15 Tuesday 25 August 2026 (37411) Print this report
DRMI LSC noise reduction

[Hirose, Tanaka, Ushiba]

Abstract:

Roll off filters were implemented into TM_OLDAMP_L filter bank of PRs and SRs.
These roll-off filters reduced the noise in PRCL, SRCL, and AS34 signals.

Detail:

In this morning, DRMI was not stable enough to continue the ASC work, so we checked the suspension motions.
Then we found that SRCL signals had no structure above 1 Hz, meaning that SRCL didn't seem to see suspension motions.

To address this issue, we implemented the roloff filters in TM_OLDAMP_L filter for PRs and SRs.
For PRs, we just implemented roll-off filters at 3 Hz while maintaining overall gains at low frequencies.
For SRs, we reduced overall gains to make the loop stable with 3 Hz roll-off filters.

Figure 1 and 2 show the filters we implemented for PRM and SRM, respectively.
Similar filters are also implemented into the other PRs and SRs.
All filters are implemented at FM3 (LOCK) of TM_OLDAMP_L filter bank.

Figure 3 - 6 show the spectra of MICH error, PRCL error, SRCL error, and sideband biuldup signals, respectively.
Black lines show the spectra before this work.
Red lines show the spectra after this work.
Blue lines show the spectra when all TM_OLDAMP_L filters are turned off.
The spectra of PRCL, SRCL, and AS34 signals improved a lot with this work.

Though blue spectra are slightly better than red spectra, we keep TM_OLDAMP_L ON because it takes a long time to calm down if there is no damping controls.
In addition, since the difference in spectra are less than 3 Hz and they do not limit the RMS, these differences should not affect both LSC and ASC.

Then, we implemented the filter in the VIS guardian.
FM3 of TM_OLDAMP_L will be turned on automatically between ALIGNED state and LOCK_ACQUISITION state.

Images attached to this report
CRY (Cryostat EX)
takashi.uchiyama - 14:36 Tuesday 25 August 2026 (37412) Print this report
Comment to Started heating the X-end cryo-duct shields (37370)
2026/08/25

Kimura, Uchiyama

Since the temperature of cryocoolers were over 280K, we reduce the heater power of the cryocoolers from 18W to 8W at 14:30.

Fig. 1 shows current source for the heater of the Arm side cryocooler.
Fig. 2 shows current source for the heater of the BRT side cryocooler.
Images attached to this comment
CRY (Cryostat EX)
takashi.uchiyama - 9:36 Tuesday 25 August 2026 (37410) Print this report
Comment to Started heating the X-end cryo-duct shields (37370)
2026/08/25

Temperature changes of the cryocoolers for the duct shield of EX and IM of ETMX.
T0: 9:37JST on 25 August.
Images attached to this comment
Search Help
×

Warning

×