Reports of 26962
MIF (General)
tomotada.akutsu - 22:30 Thursday 18 April 2024 (29273) Print this report
Finalization of IFI-IMM-PRM: Day 2

Aso, Ikeda, Hirata, Takano, Akutsu; following 29261.

Summary

Confirmed the aligned light beam POP_FORWARD reached two QPDs on the POP table, but mostly clipped at a steering mirror on the POP table. So not yet centered to these QPDs. The work is still on the way.

Details

Yesterday we tweaked IMMT1 and 2 with their oplev setpoint in yaw to their limits. So, we were worried if the actual beam might be off-centered at IMMT2. So, we started with checking this. Before that, we called PROVIDING_STABLE_LIGHT to IO Guadian to make IMC with LSC and ASC. Also, we also set IMC ASC gain to zero (following Ushiba-kun's suggestion) so that we were able to walk across the light beam to IMMT1T without disturbing the aligned IMC. Then, it seemed the spot on IMMT2 was mis-centered somehow. So, we re-considered our plan. At this point, the new plan was to (1) reset the setpoint values of IMMT1 and 2 to the values before yesterday, (2) check the IMMT2 centering, and if not good, adjust with IMMT1 setpoint, (3) align IMMT2 to center the spot on PR2 with setpoint, and (4) adjust PRM centering with its traverser.

When reset IMMT1 setpoint, the beam centering at IMMT2 seemed ok (Fig. 1) , so we simply left the IMMT1 setpoint as reset value. Then, we tweaked IMMT2 to bring the beam spot at the center of PR2 (precisely, its HR target); Fig. 2. With this situation, we checked the beam spot postion at PRM (both at AR (Fig. 3) and HR (Fig. 4) with the relevant targets; these AR and HR spot locations were almost the same), and it was 5-mm off-centered in the minus Y direction.

5-mm would be too large for the PRM traverser to move. The demerit of using the traverser are (1) the small movable limit itself as already mentioned, (2) we need to adjust oplevs otherwise we would lose ALIGNED state of PRM (ALIGNED state would be useful to control a suspension with its setpoint values), (3) even though "ALIGNED" can be obtained, this would not mean the beam reflected at PRM could reach REFL, and (4) at any rate, PRM mid baffles do not follow the move of the main suspension chain of PRM. On the other hand, considering the RoC of PRM is ~460 m (kagra wiki), 5-mm off center might be acceptable or easily to be compansated.

So, the original plan mentioned above was slightly modified: (4) not adjust PRM traverser, but adjust mid baffles for PRM later.

The PRM AR mid baffle seemingly caught two (known) ghost beams from PRM. In this sense, this mid baffle would be also ok. But in fact, looking at the aperture of the PRM AR mid baffle, the aperture edge seemed shining with IR (Fig. 5; taken from a location between IFI and IMM with the Miyakawa-san's IR camera; two ghost beam spots at IMMT1's shield can be also seen, and they may come from IFI...). This shining might be due to the main beam's slight clipping. JGW-T1910659-v2 shows where these ghost beams and main beam would come at PRM AR mid baffle, and this clipping might happen in the current situation: the main beam is shifted with respect to the aperture in the minux Y direction about 5 mm, while this document says the 2.8 sigma edge of this main beam should be nominally 4.8 mm away from the edge. So we will adjust the AR (and HR for balancing?) mid baffle position later. See also Fig. 6; also compare with 20797 and 21654.

Anyway, apart from the slight clipping at this PRM AR mid baffle, the main beam would be well aligned. Then, we detached the duct connecting the POP table and PR2 chamber to see the PR2 transmission IR beam, or POP_FORWARD. Fortunately we confirmed that this beam was somehow reaching relevant two QPDs (Fig. 7). We also confirmed this with QPDs SUM count variation. But we also found that this beam was 90%-ly clipped at a steering mirror just after the periscope (Fig. 8). It seemed no simple way to resolve this clipping...

Note

  • We confirmed that the beam spot on PR2 varied depending on the PRM state PAY_FLOAT or ALIGNED. Be careful!
Images attached to this report
MIF (General)
yuta.michimura - 19:11 Thursday 18 April 2024 (29269) Print this report
Preparations for BS transmission/reflectivity measurements with different polarizations

[Shimasue, Michimura]

We are preparing a setup for BS transmission and reflectivity measurements around IMC REFL area.

Background:
 BS is designed and measured to have 50:50 transmission and reflectivity for s-polarization (Ts=49.96%, JGW-T1503347).
 But the BS transmission and reflectivity for p-polarization are unknown (Designed to have Tp=80% or so, AR for p-pol a few %, JGW-T1503347).
 To understand what is going on in the IFO for p-pol, we are planning to measure them with an another laser source during this vent.

What we did:
 - Assembled a tripod setup with a bread board to install laser source (Attachment #1)
 - Assembled a laser injection bench on the bread board (Attachment #2, now resting on IMC REFL table)
 - Assembled a tripod setup with a bar to hold a power meter to measure the incident power to the BS and BS reflected/transmistted powerr (Attachment #3)
 - We are planning to stick this power meter to ICF203 flanges between BS and ITMX or ITMY (Attachment #4 and #5)

Images attached to this report
VIS (OMM)
ryutaro.takahashi - 14:41 Thursday 18 April 2024 (29272) Print this report
Comment to Visual inspection of Stack (29245)

[Takahashi, Ikeda]

We took pictures of the space between the SUS blocks with the fiber scope in the OMM chamber. We could see gaps around all the bellows that we could access. We could not access the 2-1, 2-3, and 3-3 bellows.

Images attached to this comment
MIF (General)
takafumi.ushiba - 9:27 Thursday 18 April 2024 (29271) Print this report
Comment to Finalization of IFI-IMM-PRM: Day 1 PM (29261)

To align GRX and find the good alignment of PR3, we first opened GVs between IX/EX and X arm.
Then, I tweeked PR3 alignment to maximize the GRX PD output, which is aligned just before the vacuum evacuation (klog29131).

After finding the good alignment, we checked the single GRX beam position on ITMX.
Figure 1 and 2 show the Tcam photos with GRX before the earthquke and now.

Though current beam seems slightly shifted from the beam before the earthquake, the amount of shift is not so large and maybe acceptable.
So, we didn't move the POMs yesterday.

After confirming these things, works in the Akutsu-san's reports followed.
 

Images attached to this comment
VIS (OMM)
ryutaro.takahashi - 8:36 Thursday 18 April 2024 (29270) Print this report
Comment to Confirmation of BB height (9555)

Please see the original report in 2019 (klog 9555).

MIF (General)
tomotada.akutsu - 6:39 Thursday 18 April 2024 (29261) Print this report
Finalization of IFI-IMM-PRM: Day 1 PM

Ushiba, Aso, R. Takahashi, Shimasue, Ikeda, Hirata, Akutsu; Ref: 16954.

Summary

Our objective is to finalize stuffs in IFI, IMM, and PRM chambers, which will be closed in the nex week. The finalization include main beam alignment and alignment relevant ghost beams to beam dumps. Today GRX path was confirmed. Alignmenf of the input IR beam axis to POP_FORWARD through PR2 and PRM is still on the way (we are at proceder #5 shown below).

Procedure planned

Refer to Fig. 1.

  1. Release PRM, PR2, and PR3 as well as relevant suspended BB (breadboard). Note that an invac (to be invac) pick-off mirror (POP-POM) is on the suspended BB. POP-POM will reflect three beams: POP_FORWARD, GRX, POP (backward). GRX and POP should overlap in the nominal case. 
  2. Find GRX transmission at TMSX by sweeping PR3. Note that PR2 and PR3 should be at ALIGNED state.
  3. Align the GRX spot on ITMX (not necessarily green flashing) to the "nice" location. The nice location should be the same one found during O4a. This align should be done with POP-POM.
  4. Check GRX spot on PR2 and PR3. For PR2, if the spot would be too much shifted, the spot should be adjusted with a (in-air) steering mirror on the POP table. For PR3, the check is just for confirmation; we may not have any knobs to adjust this on PR3.
  5. Inject IR from IMC; IO Guardian should be set "PROVIDING_STABLE_LIGHT" so that full IMC ASC should be kept. This mean the input beam axis to IMMT1T confirmed. Then do iteration with IMMT1 and IMMT2 to align beam pass through the center on PRM and a location on PR2; this location of PR2 should be, ideally, identical with the GRX path somehow determined above.
  6. Then PR2 transmission, or POP_FORWARD, should be reflected by POP-POM and comes out of the PR2 chamber to POP table, so (if necessary) adjust the relevant periscope and following steering mirrors to introduce it to the POP_FORWARD QPDs.

Actual activities

After FC works (29254), PRM, PR2, PR3, and their BBs were released as planned. For PR3 release,  as unfortunately as usual, PR3 was largely tilted and the oplev lost. The alignment was tentatively adjusted with picomotors. Fortutenately PR3 oplev came back, but one of the PR3 OSEMs would be about saturated. Because PR3 Guradian was able to reach ALIGNED, today we accepted this situation at this point. Later we need to adjust PR3 suspension manually.

Opening GRX shutter, and sweeping PR3, GRX transmission was immediately found at TMSX. The would mean that letting PR2 BB releasing/sitting might not so affect POP-POM alignment. This is good news. Also, the GRX spot at ITMX seemed almost the same as the one taken some days ago when the interferometer was nice alignment (the detail of this point will be separately reported by Ushiba-kun?)

Putting a PR2 HR target, we checked GRX spot on this target, and it was not so bad (mostly centerd but slightly shifted), so we left it as was. See Figs. 2 and 3.  Then detaching the PR2 HR target, and putting a PR3 HR target, we also checked GRX spot on this target. As written in the above planned procedure, this was just for confirmation; we could not do anything on this spot (Figs. 4 and 5). By the way, when you would insert the target, the suspension should not be at ALIGNED state, as oplev and/or OSEMs might be affected by your beam cut or light illumination. If you are very much careful, you may be able to live with ALIGNED state, though.

Then we started iteration of the IR beam from IMC. As mentioned above, to IO Guardian, we called PROVIDING_STABLE_LIGHT, which means that the input beam axis is fixed to the sub-local area around IMC, and IMMT1T QPD was used as one of references. One should not cut the beam to IMMT1T to keep this alignment control. The iteration is: (1) check PR2 HR target and IR spot on it, and adjust the IR spot on it with IMMT2, (2) check PRM AR target and IR spot on it, and adjust the IR spot on it with IMMT1. (3) Repeat from (1) until the situation converges. But, for some reason, repeating several times, the situation was not so converged. Even more, before converging, for IMMT1 and IMMT2, the oplev range and/or coil actuator range both reached limits. We may start with taking care of these tomorrow morning.

Note

  • We may not need to do too much iteration, when looking at the current beam spot positions (Fig. 6; my iphone camera somehow can see a light spot on the target illuminated with 100 mW...)
  • Ushiba-kun suggested the other way later: illuminate almost center of IMMT2, then align IMMT2 to illuminate the nice position on PR2 target, then move PRM traverser so that the PRM target was nicely illuminated. This might be partly similar to way we had done in June 2021 (16954). If someone have other posts of initial alignment for finalization after June 2021, please let us know.
  • I should have used not PRM AR but PRM HR as this reference...? -> It seems that PRM AR target was adjusted usable, according to 16954.
  • GRX beam spot on PR2 HR target will match with an IR beam reflected at PR2 but not with that of forward IR beam from IMMT2. In this sense, for example, GRX spot in Fig. 2 and IR spot in Fig. 4 should not match in yaw. See JGW-T2113078-v2.
Images attached to this report
Comments to this report:
takafumi.ushiba - 9:27 Thursday 18 April 2024 (29271) Print this report

To align GRX and find the good alignment of PR3, we first opened GVs between IX/EX and X arm.
Then, I tweeked PR3 alignment to maximize the GRX PD output, which is aligned just before the vacuum evacuation (klog29131).

After finding the good alignment, we checked the single GRX beam position on ITMX.
Figure 1 and 2 show the Tcam photos with GRX before the earthquke and now.

Though current beam seems slightly shifted from the beam before the earthquake, the amount of shift is not so large and maybe acceptable.
So, we didn't move the POMs yesterday.

After confirming these things, works in the Akutsu-san's reports followed.
 

Images attached to this comment
CRY (Cryostat IX)
nobuhiro.kimura - 6:32 Thursday 18 April 2024 (29268) Print this report
Comment to One od Cryocooler 50K Head showed strange temp enhencement (27720)

[Kimura, M. Takahashi and Sawada (Hokuto)]
On the morning of Apr. 17, one failed helium compressor (Xfs) at IXC was replaced due to a suspected IXC failure.
(klog28051)
This compressor is the compressor for IXC's duct shield cooling cryo-cooler.
The removed compressor will be repaired.

VAC (IX)
nobuhiro.kimura - 6:05 Thursday 18 April 2024 (29267) Print this report
IXC vacuum leak test results

[Kimura and Ueda (SKS) ]

On the morning of April 17, a vacuum leak test was performed on the closed flanges around IXC and IXA.
The vacuum leak test results showed a large leak of more than 3.9 x10^-9 Pam^3/s at the +Y side flange of the cross tube.
Since this leak affects the cooling of the mirror, it is necessary to repair the leak by pressurizing the vacuum chamber to atmospheric pressure.
High purity air with a low dew point was arranged for pressurization.

Images attached to this report
VAC (IX)
nobuhiro.kimura - 5:55 Thursday 18 April 2024 (29266) Print this report
Comment to Start surveying the V-type Chambers (28824)

[Araki (KEK) and M. Takase]

We finished surveying the V-type Chamber (IYV) after pumping down on Apr. 17.

VIS (OMM)
shinji.miyoki - 0:07 Thursday 18 April 2024 (29265) Print this report
Comment to Confirmation of BB height (9555)

Could you please tell us when is the last measurement? before the Noto earthquake?

VIS (OMM)
shinji.miyoki - 0:05 Thursday 18 April 2024 (29264) Print this report
Comment to Visual inspection of Stack (29245)

If so many positions are contacted, I am afraid that the optical table rotation angle may change because of the friction forces at these contacting points.

VIS (IFI)
ryutaro.takahashi - 23:39 Wednesday 17 April 2024 (29263) Print this report
Visual inspection of Stack

I checked the condition of the stack partially with an inspection mirror in the IFI and IMM chamber. I could see gaps between the SUS blocks much enough to prevent touching.

Images attached to this report
VIS (OMM)
ryutaro.takahashi - 23:01 Wednesday 17 April 2024 (29262) Print this report
Comment to Confirmation of BB height (9555)

[Takahashi, Ikeda]

We confirmed the height of the breadboard (BB) in the OMC chamber. We measured the distance between the floor level of the OMC chamber and the top of BB with the laser leveler. The BB top was (135.5-80=55.5mm) higher than the 1000mm point from the floor. This height (1055.5mm) was consistent with the last confirmation (1058-3=1055mm).

Images attached to this comment
VIS (OMM)
ryutaro.takahashi - 22:30 Wednesday 17 April 2024 (29259) Print this report
Comment to Visual inspection of Stack (29245)

[Takahashi, Ikeda]

We took pictures of all the space between the SUS blocks with the fiber scope in the OMC chamber. The conditions are summarized in the table.

O: Small gap, X: No gap, Δ: Touching or very close

Bellows 1st 2nd 3rd
1-1

O

X X
1-2 O O Δ
1-3 O X Δ
2-1 O X X
2-2 Δ O Δ
2-3 O O Δ
3-1 Δ O X
3-2 Δ X X
3-3 X - -

 

Images attached to this comment
MIR (General)
yoichi.aso - 22:19 Wednesday 17 April 2024 (29260) Print this report
Ultra-Pure Water Generator

I prepared an ultra-pure water generation system in the clean booth in front of the draft-chamber booth.

The water circulation system works fine.
However, the ultra-pure water generator (the white machine on the left of the sink) did not work so well.

First of all, the pressure gauge for the RO filter (Reverse Osmosis Membrane Filter) is broken. So we cannot confirm if a proper pressure is applied to the RO filter or not.

Secondly, the purelity of the filtered water is not good. The specific resistance of only 2M [Ohm*cm] was achieved, while it should be above 15M [Ohm*cm] to be qualify as ultra-pure water.
I changed all the filters in the machine. Still the specific resistance was around 2M [Ohm*cm].

I think we should buy a new ultra-pure water generator.
 

Images attached to this report
VAC (EYA)
takashi.uchiyama - 17:34 Wednesday 17 April 2024 (29258) Print this report
Comment to Pool of liquid in EYA chamber (29214)
2024/04/17

Sawada, Kimura, Hayakawa, Uchiyama

We performed several tests on the liquid sample.

[1] PH check
I checked the PH of the sample with a PH checker paper.
The color of the paper showed the PH is between 5 and 6. It means that the liquid has weak acidity.

[2] Pumping down test
We constructed a small vacuum system.
- Firstly, I pumped down the box while the inside was empty. The achieved pressure was 0.2 atm.
- Secondly, I put liquid inside the box and then pumped it down. The achieved pressure was 0.2 atm.
- Finally, I put the liquid added some water in the box, and then pumped it down. The achieved pressure was 0.2 atm.
We can use a strong pumping unit for this test at the next trial.

[3] Burnable test
We put a small amount of liquid in an aluminum bowl and heated it with a lighter.
The liquid was not burned.



VIS (OMM)
tatsuki.washimi - 16:24 Wednesday 17 April 2024 (29257) Print this report
Comment to Visual inspection of Stack (29245)
DGS (GPS)
shoichi.oshino - 16:14 Wednesday 17 April 2024 (29256) Print this report
Comment to Common view server troubleshooting (28969)
Today Common View came back from repair and I plugged in the cables and tried to start it up.
During this process, the connector on the GPS antenna cable came loose.
I asked Shimode-san to try to solder the coaxial cable to the connector but it did not work.
The connector fittings are thinner than the coaxial cable core and cannot be attached as it is. So the shaft was shaved to make it thinner. However, the shaft had a copper coating on the aluminum and could not be soldered. We decided to buy a Better connector that matched the shaft.
Images attached to this comment
VIS (EX)
satoru.ikeda - 15:18 Wednesday 17 April 2024 (29255) Print this report
Comment to F0Y stepper motor of ETMX somehow stopped moving (29182)

Takahashi-san, Ikeda

Continued from K-Log#29182
We have investigated the ETMX F0 YAW stepper motor not working.

We connected a single motor to the end of a DSUB cable and checked that the motor driver was working properly.

Procedure.
1. we disconnected the root of the conversion cable at the end of the feed-through flange and connected the motor we brought in to the motor driver, Fig-1.
2. drive the F0Y stepper motor from the MEDM.
Check that the motor rotates in accordance with the drive volume.

Result.
The motor rotated as expected.

From the above, it can be assumed that the motor driver is normal and the installed motor is driven.
 

Images attached to this comment
Non-image files attached to this comment
MIR (PRM)
naoatsu.hirata - 14:41 Wednesday 17 April 2024 (29254) Print this report
Comment to First contact PRM (29202)

[Hirata, Aso-san]

This morning, we pilled off FC. Still we could see some residues of FC.

  • waiting time: 17h
  • ARside: The area which we applied FC were looked crouded. So, we applied FC partially again. 15min later we pilled off. Still we can see some dots.
  • HRside: Upper left side, some dots were existed. We applied FC again and removed them. It looks no big issue on HR side.

After that, we released suspention and lower bread board. And recovered suspention.

VIS (OMM)
shinji.miyoki - 7:54 Wednesday 17 April 2024 (29253) Print this report
Comment to Visual inspection of Stack (29245)

I think we should also check the stacks for OMMT, IMMT1 and IMMT2 by the scope. IMC was already closed.

Or do you (or the PEM team) have any data for their isolation function? 

VIS (OMM)
tomotada.akutsu - 7:43 Wednesday 17 April 2024 (29252) Print this report
Comment to Visual inspection of Stack (29245)

This might be one of the main issues we can take care before O4b. A rought list of the sub tasks would include

  • Soon measure the block by block transfer functions among the stacked blocks and/or the top optical table, to check if these touching screw heads (and/or too long screw legs between the stack block and the optical table) would cause some non negligible issues ot not.
  • Depending on the results of the measurement above, insert/locate (vacuum compatible) dampers between or on the top optical table and/or the stack block(s). The damper material can be the same damping metals as added for the OMC body (M2052? according to the drawing). The main target frequency candidate might be ~30 Hz peak seen in the invac geophone spectra, or ~220 Hz excitation behavior seen in the invac geophone time series when one foot-tapped the ground outside of the OMC cleanbooth.
  • I tried to consider the way to erase the "sitting" screws and make the head thinner, but so far I do not have good idea other than the most direct way: taking out all, and do stack from the first. Such brute thing should be a thing after O4b...

Well, generally speaking, "not-reviewed installation" is mere putting stuffs but does not mean "installation completion".

CRY (Cryostat EX)
nobuhiro.kimura - 5:58 Wednesday 17 April 2024 (29249) Print this report
Replacing work for helium compressor of EXC

[Kimura, M. Takahashi and Sawada (Hokuto)]
On the afrenoon of Apr. 16, one failed helium compressor (P-55) at EXC was replaced.
(k-log 28324) 
This compressor is the compressor for EXC's radiation shield cooling cryo-cooler.
The new connecting piping and filter need will be connected.
The removed compressor will be repaired.

VAC (IX)
nobuhiro.kimura - 5:51 Wednesday 17 April 2024 (29251) Print this report
Comment to Start surveying the V-type Chambers (28824)

[Araki (KEK) and M. Takase]

We finished surveying the V-type Chambers (IXV and EXV) after pumping down.

VAC (Valves & Pumps)
nobuhiro.kimura - 5:35 Wednesday 17 April 2024 (29248) Print this report
Comment to Strange shhhh sound around TMSX pendulum valve (28628)

[kimura]

The parallel threaded seal joint with O-ring, which was the cause of air leakage in the valve drive of the GVetmx, was replaced with a regular tapered threaded seal joint.
After the replacement, a leakage test was conducted, and it was confirmed that there was no leakage.
Replacement with tapered thread seal joints is required for all KAGRA φ1000 gate valves, φ800 gate valves, and pendulum valves.
The following three gate valves are awaiting replacement.
1. GVitmx
2. GVitmy
3. GVetmy
 

Search Help
×

Warning

×