We are preparing for the installation of the Ncal system. As part of this preparation, we checked the installation area and confirmed the tools, space, and cable routing needed for the pylon and Ncal installation work.
The following items were checked at the site:
- We placed the full-scale drawing of the pylon at the planned installation location. No serious issue was found. We also measured the distance to nearby structures, and the closest clearance was about 3 cm.
- We confirmed that a lifter, Bishamon, is available at the Xend.
- We checked the possible location for hanging a chain block. The floor of the mezzanine level was inspected for this purpose.
- We confirmed that the parts of the gantry crane exist at the site. However, we probably will not use it for the actual installation work.
- We took site photos of the possible routes for the signal cables and power cables.
The site photos will be shared later.