Reports 1-1 of 1 Clear search Modify search
FCL (Inflastructure)
shinji.miyoki - 14:00 Saturday 28 February 2026 (36467) Print this report
SR-OMC area cleaning day2

[Miyoki]

The Fujimi-sangyou member found a huge water pool on the ceiling just above the -X side of the SRM vacuum tanks. (Maybe Hayakawa-kun also noticed well before) (Photo.1)

Although the water drain pipe was set just around this pool, there seems to be no water flow in this drain pipe, maybe because something is stuck at some point. So we tried to drain this water along some possible paths by pushing up the water pool with several T-bars. Fortunately, about 70% water could be drained out. (Photo.2) We need to fix this drain system while the amount of water is small. 

Images attached to this report
Comments to this report:
shinji.miyoki - 18:36 Saturday 28 February 2026 (36468) Print this report

2 FFUS were recoverd above SRM by reconnecting power/line cables near FFUs. 1FFU above SR3 and OMMT was still off maybe because of power/signal line disconnection.

Wrapped stainless steal floors near SR2 and SRM were repaired.

Images attached to this comment