VIS (EY)
takaaki.yokozawa - 8:19 Tuesday 06 January 2026 (36030) Print this report
Suspension commissioning 2026 ETMY
I started the suspension commissioning ETMY
First, I measured the spectrum with excitation.
Fig.1 - Fig.6. showed the results compared with the July 2024
Images attached to this report
Comments to this report:
takaaki.yokozawa - 8:35 Thursday 08 January 2026 (36066) Print this report
I performed the NBDAMP tuning for L1, L2 and L3.
Fig.1. - Fig.3. showed the OLTF for each filters.
L1 : Using FM4 filter
L2 : Using FM1 filter
L3 : Using FM1 filter

Since, we cannot find the good filter for L5, I turned off for the 300K case.
We will check the long stability without L5 filter.
Images attached to this comment