We have begun preparations for installing the GVommt interlock device.
The initial plan was to complete installation today, but it became apparent that time is needed for preparations such as routing network cables.
Therefore, we confirmed the installation location for the interlock control rack and placed it temporarily. Please refer to the attached photo for the temporary placement location.
Next time, we plan to purchase the network cables, switches, and fiber optic cables and propose a schedule for their installation.