[miyoki, yuzurihara, uchiyama, yoshimura, takahashi.m, omae, sawada]
We have finished the cleaning at IXC(1F,2F), IXV, EXC(1F,2F) and EXV.
The temp adjustment is ongoing for each area by operating FFUs, KOACHs, heaters, and air coolers.
[miyoki, yuzurihara, uchiyama, yoshimura, takahashi.m, omae, sawada]
We have finished the cleaning at IXC(1F,2F), IXV, EXC(1F,2F) and EXV.
The temp adjustment is ongoing for each area by operating FFUs, KOACHs, heaters, and air coolers.
[miyoki, yokozawa, yoshimura, takahashi.m yamaguchi, omae]
We finished the cleaning at EYC and EYV.
IXA area cleaning was finished. On the other hand, we postponed the cleaning of IYA because there is a tunnel.
[miyoki, fujii, ohmae, yamaguchi, takahashi.m]
We finished the cleaning at EYA and TMSY.