Springwater was found in the pit at the back of IXC clean booth KOACH filters. A small water pump will be used at this position.
The water dropping in the arm tunnel is now increasing according to hayakawa-kun.
Springwater was found in the pit at the back of IXC clean booth KOACH filters. A small water pump will be used at this position.
The water dropping in the arm tunnel is now increasing according to hayakawa-kun.
Current status of the water fluid meter at Y-end
The water pumps in the Y-arm might be operated this weekend to avoid flooding. At this moment, I guess almost water will not be introduced in the EYC area.
The water pump didn't work on the last weekend.
I compared the flow rate between this year and last year.
Increasing the drain water is getting slow.
Increasing of the water drain is stopped?
The flow rate backs to increase.
The pumps didn't work in this weekend.