[Kimura, Uchiyama, Miyoki]
We did EYC/V leak procedure.
10:00 : After checking the Y-arm GR flash by Ushiba-kun, Kimura-san closed GV_eya.
All TMPs and scrole pumps were turned off with proper GV/Diaphragm-valve closing around TMPs. Two back pressure prevention valves were set around EYC. The leak at 20 litter/min has started at the TMP unit on EYV around 11:00. About 1 Pa/min is now obtained. We need to enhance ~40 litters to finalize leaking until the next Monday morning.
Kimura-san noticed that EYC vacuum level unusual enhancement aroud the timing of the erathquake at 10:31 (@Ishikawa, 5+, M5.0).