VAC (IMM)
takashi.uchiyama - 17:33 Wednesday 08 May 2024 (29428) Print this report
Closing work around the IMM chamber
2024/05/08

Kimura, mTakahashi, Sawada, Nakajima

We closed flanges and bellows ducts around IMM.

- The bellows duct between IFI and IMMT
- The ion pump has been reconnected to the pumping unit at the bellows duct between IFI and IMM
- dia 400 flange (No. 2-7)
- ICF203 flange (No. 2-4)
Images attached to this report
VAC (IMM)
nobuhiro.kimura - 7:10 Saturday 04 March 2023 (24259) Print this report
Evacuation work for IMM~PRM

Abstract:
 We pressurized IMM~PRM up to atmospheric pressure on 3/Mar./2023.

Workers: 
N. Kimura and H. Yasui

Images attached to this report
VAC (IMM)
takashi.uchiyama - 8:13 Monday 31 October 2022 (22737) Print this report
Pumping unit between IFI and IMMT has been turned off
2022/10/28

Uchiyama

I turned off the pumping unit between IFI and IMMT at 11 AM on October 28, 2022.
VAC (IMM)
shinji.miyoki - 9:44 Friday 21 October 2022 (22608) Print this report
Comment to Started the vacuum leak test from PRM to IFI (22561)

Additional Information.

Kimura-san found that some of the nuts in the tie rods between the GV_mcf and the MCF tank, and between the MCF tank and the duct were not tightened! These could be the momentary leak of IMC.

Kimura-san checked any leaks in the 1000 flanges around the MCF tank and 400 flanges towards the PSL room. However, no leak was found. We optimistically guess the leaking point was pressed back again.

VAC (IMM)
nobuhiro.kimura - 15:25 Thursday 20 October 2022 (22582) Print this report
Comment to Started the vacuum leak test from PRM to IFI (22561)

When: 19/Oct./2022

Who: Kimura, Yasui, M. Takahashi and Ueda (SKS)

Task:
We performe vacuum leak test from IMMT and IFI, and found large vacuum leak with level of ~1 x 10^-9 Pam^3/s at connection between IFI and beliow duct.   

We repared the leak and comfirmed level of leak was < 1 x 10^-13 Pam^3/s.

Five connection flanges remain untested.

The leak test will be continued and completed on the morning of October 20.

VAC (IMM)
nobuhiro.kimura - 15:24 Thursday 20 October 2022 (22592) Print this report
Comment to Started the vacuum leak test from PRM to IFI (22561)

When: 20/Oct./2022

Who: Kimura, Yasui, M. Takahashi and Ueda (SKS)

Task:
We performed  vacuum leak test for left five connection flanges on IMMT and IFI, and confimed there were no large vacuum leak with level of > 1 x 10^-10 Pam^3/s.   

The vacuum  leak test for IFI, IMM and PRM was completed. 

We will start vacuum  leak test for TMSY on 21/Oct.. 

VAC (IMM)
nobuhiro.kimura - 20:35 Tuesday 18 October 2022 (22561) Print this report
Started the vacuum leak test from PRM to IFI

When: 18/Oct./2022

Who: Kimura, Yasui, Uchiyama and Ueda (SKS)

Task:
We started vacuum leak test from PRM to IFI, and found large vacuum leak >~2 x 10^-10 Pam^3/s.

As reported by Ushibasan (k-log22557), we repared the leak and comfirmed level of leak was < 1 x 10^-13 Pam^3/s.

We will continue to have leak test on 19/Oct., and comple it.

Comments to this report:
nobuhiro.kimura - 15:24 Thursday 20 October 2022 (22592) Print this report

When: 20/Oct./2022

Who: Kimura, Yasui, M. Takahashi and Ueda (SKS)

Task:
We performed  vacuum leak test for left five connection flanges on IMMT and IFI, and confimed there were no large vacuum leak with level of > 1 x 10^-10 Pam^3/s.   

The vacuum  leak test for IFI, IMM and PRM was completed. 

We will start vacuum  leak test for TMSY on 21/Oct.. 

nobuhiro.kimura - 15:25 Thursday 20 October 2022 (22582) Print this report

When: 19/Oct./2022

Who: Kimura, Yasui, M. Takahashi and Ueda (SKS)

Task:
We performe vacuum leak test from IMMT and IFI, and found large vacuum leak with level of ~1 x 10^-9 Pam^3/s at connection between IFI and beliow duct.   

We repared the leak and comfirmed level of leak was < 1 x 10^-13 Pam^3/s.

Five connection flanges remain untested.

The leak test will be continued and completed on the morning of October 20.

shinji.miyoki - 9:44 Friday 21 October 2022 (22608) Print this report

Additional Information.

Kimura-san found that some of the nuts in the tie rods between the GV_mcf and the MCF tank, and between the MCF tank and the duct were not tightened! These could be the momentary leak of IMC.

Kimura-san checked any leaks in the 1000 flanges around the MCF tank and 400 flanges towards the PSL room. However, no leak was found. We optimistically guess the leaking point was pressed back again.

VAC (IMM)
takashi.uchiyama - 8:46 Saturday 01 October 2022 (22293) Print this report
Closing IMMT chamber
2022/09/30

Mirapro, Kimura, Uchiyama

We closed the ICF203 flange at the +X+Y side of IMMT by a blank flange.
Also, we closed the K400 flange at the -Y side of IMMT by a metal Oring.

All the flanges of IMMT have been closed.
VAC (IMM)
takashi.uchiyama - 8:39 Friday 30 September 2022 (22269) Print this report
IFI and IMMT have been connected
2022/09/29

Mirapro, Kimura, Uchiyama

We connected IFI and IMMT by a bellows duct with a pumping unit.
We used elastomer O rings.

For this work, we moved the ISS table.
VAC (IMM)
takashi.uchiyama - 8:49 Thursday 29 September 2022 (22239) Print this report
IMMT and PRM have been connected
2022/9/28

Mirapro, Kimura, Ushiba, Akutsu, Yokozawa, Uchiyama

We connected the IMMT chamber and the PRM chamber by a bellows duct.
We used metal Orings.
VAC (IMM)
takashi.uchiyama - 8:33 Friday 24 December 2021 (19310) Print this report
Install a conversion flange of ICF203 to 152 at the +Y side of the IMM chamber
Sawada, m Takahashi, Uchiyama

2021/12/23

They installed a conversion flange of ICF203 to 152 at the +Y side of the IMM chamber for ISS.
Images attached to this report
VAC (IMM)
yutaro.enomoto - 14:02 Thursday 04 October 2018 (6417) Print this report
Open and Close of the Top Flange of IMM Chamber

[Mirapro people (Itoh-san, Shimizu-san), Observer: Enomoto]

They opened and closed the top flange of IMM chamber.
They replaced O-rings.
They found that a tiny piece of plastic tape was caught between the chamber and the flange (see the picture).
Note that a O-ring accidentally dropped inside the chamber when they were opening the flange, but no damages for IMMT1 were found.
I also attach the trend of IMMT1 oplev outputs.

Images attached to this report
VAC (IMM)
takashi.uchiyama - 16:36 Sunday 11 March 2018 (4410) Print this report
Vacuum duct between IMM-PRM was fixed
Mirapro fixed the vacuum duct between IMM-PRM on 11th March.
VAC (IMM)
takashi.uchiyama - 11:51 Friday 26 February 2016 (847) Print this report
A vacuum duct between IMM and PRM has been connected
@2/23

A vacuum duct between IMM and PRM has been connected.
In this work, the working place was sandwiched by two KOACH filters.

We found height difference between the flange of IMM and PRM by 11mm because of tilting up of beam level by 1/300 from the MMT2 mirror in IFI.
So that bellows part in the duct was forced to be deformed largely.
VAC (IMM)
takashi.uchiyama - 10:14 Friday 26 February 2016 (840) Print this report
A vacuum duct between IMM and IFI vacuum chamber has been connected
@2/22-23

Mirapro connected a vacuum duct between IMM and IFI.
During this work KOACH filters were placed at a 400 dia. flange of both IMM(PRM side) and IFI(GVmc side).

When we put the duct on supporting legs, we found the legs were too tall.
So that we removed the legs and asked MESCO to make the legs 10cm shorter.
The duct was suspended 5cm higher than designed position.

We started connection work of a duct between IFI and GVmc.
In this work, we placed three KOACH filters at a 400 dia. flange of both IMM(PRM side) and IFI(MCE side) and between IFI and GVmc.

After connecting the duct between IFI and GVmc, we noticed that we could connect the duct between IMM and IFI without the legs.
We connected the duct between IMM and IFI and all the flanges for the KOACH filters were closed.

In the tomorrow morning (2/23) we received the shorter legs.
We placed two KOACH filters at a 400 dia. flange of both IMM(PRM side) and IFI(MCE side).
The duct between IMM and IFI was once removed from the vacuum chambers, put on the shorter legs, and connected again.


VAC (IMM)
takashi.uchiyama - 9:39 Friday 04 September 2015 (52) Print this report
Stack vibration isolation system has been installed in the IMM chamber.
Stack vibration isolation system has been installed in the IMM chamber.

We found two bellows at the bottom mass were damaged, so that we changed those bellows with spare bellows before installation.
VAC (IMM)
takashi.uchiyama - 23:17 Wednesday 02 September 2015 (46) Print this report
A base plate has been installed in the IMM vacuum chamber.
A base plate has been installed in the IMM vacuum chamber.
All the screws have been inserted without problem.