VIS (SR2)
mark.barton - 23:07 Tuesday 20 November 2018 (7065) Print this report
SR2 Installation

With Akutsu-san, Enzo, Hirata-san and Fabian.

Today:

  • With supervision by Akutsu-san, we installed the OL TX pillar and RX shelf. We had all the parts we needed except 4 x M12 washers and 2 x M12 nuts for the shelf (which we ran out of halfway through), so the shelf is currently held by only two of four screws. (We will also need an full set of 8 washers and 4 nuts for SRM, for a total of 12 washers and 6 nuts.)
  • Again with supervision from Akutsu-san, we installed the two viewports for the OL, serial numbers #24 (at the bottom) and #25 (at the top).