Reports 1-1 of 1 Clear search Modify search
VIS (General)
daisuke.tatsumi - 8:03 Friday 29 January 2016 (699) Print this report
VIS weekly report from TATSUMI [2016-01-29]

Weekly report on 2016-01-29

* PR3

  * PR3 flag and 2nd wire breaker repair status (Tatsumi)

     o PR3 mirror and its mirror box came back to Mitaka [Ishizaki, Jan 28]

        Dropped flag and 2nd wire breaker are included in the box, aren't they? Not yet checked.

    * Glueing JIG parts will be received. Hirose-san will send these. [Feb 1]

    * Try to clean up the mirror and dropped parts [Jan 30]

    * Gleing work [Feb 2]

    * Shipping to Kamioka [Feb 5, Fri]

 

* iKAGRA ETM suspension

  * PRM transportation (Tatsumi)

    o Thin plates to protect magnets arrived. [Ohishi, Jan 18]

    * Plastic containers were ordered by Hirose. Delivery date: [Feb 2 @Kashiwa, Feb 4 @Mitaka]

    * Shipping to Kamioka [Feb 5, Fri]

 

[[ Footnote ]]

These marks show "o"; done and "*"; to do.

Search Help
×

Warning

×