Weekly report on 2016-01-29
* PR3
* PR3 flag and 2nd wire breaker repair status (Tatsumi)
o PR3 mirror and its mirror box came back to Mitaka [Ishizaki, Jan 28]
Dropped flag and 2nd wire breaker are included in the box, aren't they? Not yet checked.
* Glueing JIG parts will be received. Hirose-san will send these. [Feb 1]
* Try to clean up the mirror and dropped parts [Jan 30]
* Gleing work [Feb 2]
* Shipping to Kamioka [Feb 5, Fri]
* iKAGRA ETM suspension
* PRM transportation (Tatsumi)
o Thin plates to protect magnets arrived. [Ohishi, Jan 18]
* Plastic containers were ordered by Hirose. Delivery date: [Feb 2 @Kashiwa, Feb 4 @Mitaka]
* Shipping to Kamioka [Feb 5, Fri]