masayuki.nakano - 19:23 Tuesday 03 April 2018 (4617) Print this report
The commissioning works on 4/3

[Izumi, Nakano]

The commissioning works on 4/3.

Check wiring around REFL PD
 PDA100 -- BNC-RFPD interface(k1imc0)
IFO REFL RFPD -- RFPD interface(k1ioo)

Check PDs
Confirm the change of the output of PDs with/without light in RTM. Both are fine.

IQ demodulator balancing preparation
We have done equipment preparation and wiring, but since the digital system did not work well, the measurement will be done tomorrow. 