VIS (EY)
ryutaro.takahashi - 22:05 Thursday 23 February 2017 (2536) Print this report
Preparation of the F3 stage
[Takahashi, Ishiszaki, Sato, Shindo]

1) Fixed the additional weight for the dummy payload by PEEK ties.
2) Lifted down the EQ stop into the chamber and put the end plate for BF on the frame rock.
3) Set the footholds around the top chamber. Side bars were connected.
4) Extended the third rods with the shield plate upto the F3 stage.
5) Assembled the end plate for F3. The release sensors were attached and cabling was applied.
6) Put the end plate on the third rods. Checked vertical line by a laser leveler.
7) Started the cabling for the F3 (LVDT, Sttepping motor).
Images attached to this report