[Takahashi, Ishizaki, Okutomi]
EYV:
-
Pre-assembling of the BF damper is ongoing
- Screws, washers and other small parts such as cable clamps are arranged
- The palettes and the hand lifter washed yesterday are now wrapped and got ready to use
EYC 2F:
-
Stainless plates are laid on the floor
- They are not fixed yet, will be fixed with alminum tapes
-
The protection net is assembled but could not be installed into the cross chamber
- We check which dimension is wrong
- Anyway the flame of the net will be sent to Mitaka and go on a diet by additional machining
Photos >>> https://goo.gl/photos/ouqwj1FyvY3VNQR16