CRY (Cryo-payload IX)
takafumi.ushiba - 18:29 Wednesday 10 February 2021 (15980) Print this report
Cabling check of ITMX after installation

[Tomaru, Ushiba]

We checked the cables of cryogenic payload sensors and actuators.
We fixed the cables for TM actuators and MNR thermometer, which are found to be strange yesterday.

We plan to do the final check in the Friday morning.

Comments to this report:
takafumi.ushiba - 13:50 Wednesday 17 February 2021 (16044) Print this report

Tomaru-san cleaned up the cables inside the cryostat yesterday, so I checked all cables again today.

I found three cables are shorted somewhere.
This should be investigated and repaired soon.