[Tomaru, Nishimoto, mTakahashi, Ushiba]
The upgrade of EX payload.was started
The magnets on IM was replaced to new ones (larger ones).
We also installed a heater on IM and new moving mass on MN today.
[Tomaru, Nishimoto, mTakahashi, Ushiba]
The upgrade of EX payload.was started
The magnets on IM was replaced to new ones (larger ones).
We also installed a heater on IM and new moving mass on MN today.
[Tomaru, Nishimoto, mTakahashi, Ushiba]
We continued the upgrade work.
Actuators and sensors on MN stage were installed.
Remaining thing is installation of actuators on IM stage and cabling.
[Tomaru, Nishimoto, Ushiba]
We couldn't finish the cabling today.
So, we will continue it in the next week.
[Tomaru, Ushiba]
This is the post of yesterday work.
We continued EX cabling.
Not yet finished and we probably need additional one or two days.
[Tomaru, Ushiba]
We continued cabling work in this morning.
We need additional one day for finishing the work.
After that, acceptance check before installation will be started.